2026 Utility Projects Engineering Design

Midlothian

Summary

Partnering with private development to install a 16-inch water line along FM 1387 now to avoid higher future construction costs when TxDOT widens the road.

At a glance

Total mentions
2
Last 30 days
0
Importance
4

Declining — being discussed less frequently. 0 mentions in the last 30 days, 2 the 90 before that.

Impact analysis

💰Financial impact

Project cost of $236,037.50 plus contingency, funded through the utility fund.

✅Who benefits

Future utility customers and city taxpayers by avoiding costly road reconstruction tear-ups.